Updated 9 July 2017

Overall, the redevelopment project is 70% complete with the roofing and cladding of the basketball facility complete and substantial progress with roof cover, cladding and major services fit out for the football building.


The project is progressing according to schedule with several key points recently achieved;

  • The new Western Power switchgear is now live having been activated on 30 May 2017.
  • Running Bare works have commenced with brickwork, steel framework, roofing and service pre-lays in progress.
  • Landscaping at the entry to HBF Arena has commenced.

VenuesWest is proud to partner with the City of Joondalup, Department of Finance, West Perth Football Club, Wanneroo Basketball Association and the Department of Sport and Recreation to deliver these new facilities and infrastructure.

VenuesWest also acknowledges the financial support from the State Government, City of Joondalup and LandCorp to deliver this major development.